May 21, 2000

Sirajganj, UNB) – The fate of a number of development projects taken up in northern region under Annual Development Program(ADP) hangs in the balance due to unusual delay in fund allocation.

 

Officials said usually the government allocates funds for implementing ADP projects in two phases during August-February period.

 

But this year, they said, funds for ADP projects in 124 upazilas of 16 northern districts were sanctioned in six phases, creating uncertainty about the implementation of the projects.

 

Only 45 percent works of the schemes, taken up mainly in transport, heath, education and agriculture sectors, have so far been completed with the funds of 1st and 2nd phase allocations.

 

As per the government budgetary rules, the unused funds will have to be refunded to the concerned ministries if the remaining works on the projects cannot be completed by June 30.

 

As the time for implementing the projects running out, local authorities are putting pressure on the concerned firms to complete their works within the stipulated time.

 

Taking advantage of the situation, the contractors are trying to hurriedly complete the schemes using low quality materials.